This is the saga of The Barn.
We decided to find a company that not only would sell us the barn but
would handle the contracting to erect it as well, so we chose to deal with Morton
Buildings in Brownsville, Tennessee.
|
|
|
|
|
|
|
In January, we laid out the outline so we could figure out where to place it on the property. |
|
|
|
|
|
|
|
|
|
|
|
|
We had to leave room for septic field lines behind the barn because that is the way the land slopes.
|
|
|
|
|
|
|
|
|
|
|
|
|
In February, Terry Hooper completed the dirt work. This first photo is half-way through the job. |
|
|
|
|
|
|
|
|
|
|
|
|
Here the barn is re-laid out on the new pad. |
|
|
|
|
|
|
|
|
|
|
|
|
On March 16, the materials were delivered. Here are the 36 foot trusses. |
|
|
|
|
|
|
|
|
|
|
|
|
Unloading more of the barn. |
|
|
|
|
|
|
|
|
|
|
|
|
One of the neighbor's dogs came to see what was up and decided to claim each pile as the driver unloaded them. By peeing on them. |
|
|
|
|
|
|
|
|
|
|
|
|
Once construction started, it didn't take Rusty and his crew long to get the layout right and sink the beginning of the posts. |
|
This is what the scene looked like at the end of Day 1 (Thursday, March 22). They have the walls built sitting on the ground.
|
|
|
|
|
|
|
|
|
|
|
Now for the amazing transformation. These are shots at the end of Day 2 (Friday, March 23). |
|
|
|
|
|
|
|
|
|
|
|
|
The barn is 36 by 45 feet.and the end doors are 16 feet wide, 10 feet tall. |
|
There is a 6 foot overhang on the back to keep tractor implements and other stuff (more or less) out of the rain. |
|
|
|
|
|
|
|
|
|
|
On Monday, March 26, they had most of the siding completed. |
|
|
|
|
|
|
|
|
|
|
|
|
Rusty said they'd have the building up by Wednesday, and it looks like he might just be right. |
|
For some reason I think they've done this before. Then the plumbing will be roughed-in, the concrete poured and then last are the overhead doors. |
|
|
|
|
|
|
|
|
|
|
It rained Wednesday, March 28, and made the site messy, but the crew worked anyway, and this is what it looked like this morning (Thursday). |
|
|
|
|
|
|
|
|
|
|
|
|
Rusty called and said they'd not be working Thursday, but said the crew will be back on Friday to wrap up the steelwork. |
|
|
|
|
|
|
|
|
|
|
|
|
The plumbers came Thursday morning to do the rough-in as well. 'Twas a wee bit muddy. |
|
|
|
|
|
|
|
|
|
|
|
|
Saturday, March 31. We had a spring frog-strangler, so we didn't go see the finished work because we'd have sunk up to our knees in the mud. |
|
|
|
|
|
|
|
|
|
|
|
|
We went to see it Sunday near dark. Here is the finished metalwork. |
|
|
|
|
|
|
|
|
|
|
|
|
The weathervane still thinks North is East. |
|
|
|
|
|
|
|
|
|
|
|
|
Friday, April 6. The overhead doors went in today. |
|
|
|
|
|
|
|
|
|
|
|
|
Monday, April 23. The concrete forms are down. |
|
|
|
|
|
|
|
|
|
|
|
|
Looking out one of the overhead doors. There is a 4 foot pad outside each door. |
|
|
|
|
|
|
|
|
|
|
|
|
These are the forms for the 6 foot overhang on the back side. |
|
|
|
|
|
|
|
|
|
|
|
|
Tuesday, April 24. Yep, nearly 3 weeks later. The concrete is done! |
|
|
|
|
|
|
|
|
|
|
|
|
Showing the entry door and its pad. |
|
|
|
|
|
|
|
|
|
|
|
|
|
The finished overhang concrete. |
|
|
|
|
|
|
|
|
|
|
|
|
Saturday, August 11. Complete with some landscaping (i.e., sod) and gravel for the drive. |
|
|
|
|
|
|
|
|